JOINT PIPELINE OFFICE

Weekly Report 6/4/03

For additional information, contact Rhea DoBosh at (907) phone 257-1338, fax 257-1397

 

TAPS Oversight – Compliance Monitoring/ Surveillances:

               Verification of compliance with Stipulation 1.18.1, Surveillance and Maintenance and Stipulation 1.21.1, Conduct of Operations at the Valdez Marine Terminal (VMT) on the compressor lube oil reservoir in the Compressor Building.  VMT-03-S-005

Verification of compliance with Stipulation 1.18.1, at the VMT Power House.  VMT-03-S-006

               Verification of selected Grant/Lease Stipulations and the evaluation of agency permit authorizations issued for the mainline integrity investigations performed in the Pump Station 4 area.  A subsequent surveillance will address the site restoration and erosion control at the project site.

FBU-03-S-002.   

 

The following surveillances to verify compliance with Stipulations 1.18.1, Surveillance and Maintenance and Stipulation 1.21.1, Conduct of Operations, follow-up Alyeska’s efforts to analyze, identify, or detect deficiencies and then correct them utilizing the Reliability Centered Maintenance (RCM) process.  RCM methodology is used to identify failure management policies necessary to preserve the functions of critical TAPS systems. 

 

Pump room gas detection system at Pump Station 9.  FBU-03-S-014

Fire protection system at Pump Station 4.  FBU-03-S-018

Fire protection system at Pump Station 9.  FBU-03-S-005, 006, 007, 011, 012, 013, 019, 

020, 024, and 025.

Pump Station 5 pipeline tanks.  FBU-03-2-004 and 008, 009, and 010.

Backpressure control valves and pressure relief system in the VMT East Metering.  VMT-03-S-008 and 009.

Three surveillances were performed at Pump Station 5 on the following:

·        Crude tank – valves.  FBU-03-S-015

·        Hydraulic skid – piping and electrical system.  FBU-03-S-016

·        Hydraulic skid – mainline pumps and drivers.  FBU-03-S-017

 

Kenai-Kachemak Pipeline:

               A few updates from last week’s construction monitoring follows:

·        With the exception of pipe associated with horizontal directional drilling, the entire pipeline is buried. 

·        Crews were cleaning and dressing up the right-of-way in areas where pipe installation was complete.

·        Milepost signs were being placed at one-mile intervals along the right-of-way. 

              

JPO People on the Move: 

               Jim Lusher, JPO Operations Manager, will be moving on to a position with BLM in Oregon some time this summer. 

 

 Media:

               The Fairbanks Daily News Miner requested information related to TAPS strategic reconfiguration. 

 

XXX

               To receive weekly reports via e-mail, contact Rhea DoBosh at RDOBOSH@jpo.doi.gov.

              Check out JPO’s homepage at http://www.jpo.doi.gov. 

              The Joint Pipeline Office is a consortium of six State and six Federal agencies with oversight responsibilities for the Trans-Alaska Pipeline System and other oil and gas pipelines in Alaska.  The JPO came into existence in 1990 and stemmed from a cooperative effort by the Bureau of Land Management and the Alaska Department of Natural Resources.